Pad reduction and site restoration after drilling

A drilling location is built bigger than a producing well needs. Once the rig is gone, most operators cut it back, and when a well is finally plugged, the land goes back to the landowner. Both are dirt work, and both go better when they were planned for when the pad was built.

Interim reduction

After drilling and completion, the pad is reduced to what production needs: room for the wellhead, the equipment and a truck to turn around. The work usually means:

  • Pulling up rock outside the production footprint
  • Respreading the topsoil that was stockpiled when the pad was built
  • Grading so water drains off the way it did before
  • Reseeding the reclaimed area

This is why stripping and stockpiling topsoil at the start matters. Topsoil that was pushed into a berm and left is far easier to put back than topsoil that was buried under fill.

Final restoration

When a well is plugged and the location is abandoned, the rest comes out: remaining rock, the pad, the lease road if the landowner does not want it, fence and cattle guards that are no longer needed. The site is graded, topsoil goes back and the area is reseeded.

What the land must look like at the end is usually set out in the lease or the surface use agreement. Read it before the work is bid.

Plan it at the start

If you are building a pad now, tell us how much of it you expect to reduce later. It changes where topsoil gets stockpiled and how the rock goes down.

See pad construction and jobsite cleanup, or request a bid.